Electrical Systems
Registration, permits and fees for electrical systems.
The Electrical Section—in accordance with territorial and federal legislation—is responsible for establishing and interpreting the Electrical Protection Act, codes, standards and regulations to ensure installation and product safety compliance.
This section provides current information to the electrical sector and other jurisdictional authorities.
Codes and Standards
"7. (1) Subject to this Act, all electrical work and equipment must conform to the standards set in the prescribed edition of the Code."
Electrical Code
The electrical code and standards are part of the Regulations to the Electrical Protection Act. For your convenience, the codes have been extracted—but the codes in the Regulations are official.
Electrical Safety Codes
Subject to the amendments set out in Schedule B, the edition of the Code authorized by subsection 7(1) of the Act, and adopted under subsection 22(2) of the Act, is
Canadian Standards Association Standard C22.1, Canadian Electrical Code Part I, Twenty Third Edition, Safety Standard for Electrical Installations.
The following standards are adopted:
(a) Canadian Standards Association Standards:
C22.3 No. 1-06, Overhead Systems,
C22.3 No. 3-98, (R2007), Electrical Coordination,
C22.3 No. 4-1974, (R2004), Control of Electrochemical Corrosion of Underground Metallic Structures,
C22.3 No. 7-06, Underground Systems,
CAN/CSA-C61400-1-08, Wind Turbines – Part 1: Design Requirements;
CAN/CSA-C61400-2-08, Part, Wind Turbines – Part 2: Design Requirements for Small Wind Turbines;
CAN/CSA-C61215-08, Crystalline Silicon Terrestrial Photovoltaic (PV) Module – Design Qualification and Type Approval;
(b) National Research Council of Canada – National Building Code of Canada, section 9.34, Electrical Facilities.
SCHEDULE B
ALTERATIONS FOR THE NORTHWEST TERRITORIES TO THE CODE
There are currently no alterations to the Code in the Northwest Territories.
Standards Organizations
To help you know if an electrical product is approved, the following is a list of certification organizations that the Standards Council of Canada has accredited as acceptable to certify electrical equipment and products for use in Canada. When purchasing electrical equipment, specify that the product must be approved and look for the certification mark.
Recalls and safety alerts
Registration
All Qualified Electrical Workers and Electronic Technicians must be registered under the Electrical Protection Act. Registration is valid for a term of 3 years.
- Qualified Electrical Worker or Electronic Technician Registration
- NWT Power Corporation Plant Operator Registration
To register or renew your registration, download and complete the appropriate form. Once you have completed the form, send it via email along with the appropriate fee to: elecmechsafety@gov.nt.ca.
Permits
Once registered, a valid permit is required before you start work on any type of electrical or electronic installation in the NWT.
Download and complete the appropriate form. Once you have completed the form, send it via email along with the appropriate fee to: elecmechsafety@gov.nt.ca.
Electrical Permits
Wiring Installation Permit Application
Required for certified electric workers and property owners in the NWT, whether undertaking a new installation, rewiring, or addition to an existing installation.
Electric Energy/Conceal Rough Wiring Permit Application to Supply
To ensure that work done follows the permit, code, and is safe for the supply of electric energy and safe to make roughed-in work inaccessible.
Learn about Residential Property Owner’s permits.
Fees
Refer to the fee tables; please check against the formula provided in the Electrical Protection Regulations (Schedule A).
Temporary service: $91 for the first 100 amps, plus $48 for every additional 100 amps.
Fees can be paid by credit card. To make arrangements, call (867) 767-9043.
Inspections
In communities where an Electrical Inspector is available, up to three inspections may be performed for the cost of the permit fee, including:
- Permission to Make Roughed in Electrical Work Inaccessible
- Authorization for Power Connection
- Final Inspection
In communities where a physical inspection cannot be done within 14 days of notification—and the installation was done by a Qualified Electrical Worker—the first two inspections may be approved if the Qualified Electrical Worker forwards a completed Statutory Declaration by fax, followed by a phone call to the Regional Electrical Inspector.
Bulletins
Electrical
- Adoption of the Canadian Electrical Code, Part One
- Permits Required
- Expiry Dates of Permits
- Electrical Contractor Deficiencies
- Requests for Inspections
- Residential Property Owner Permits
- Mine Jurisdiction Bulletin
- Requirements When Upgrading Consumer's Services
- Ground Normally Accessible to Pedestrians
- Underground secondary specifics for residential electrical services standards (Northland Utilities)
- Self Contained Meter Isolation (Northland Utilities)
- Reconnection of Consumer Services
- Consumer's Service Conductors Entering a Building
- Photo Voltaic Installations
- Clarification of Rules on Propane
- Interpretation of Receptacles for Dwelling Units
- Wiring of Communications Circuits
- Maintenance by Power Engineers or Certified Oil Burner Mechanics
- Clarification of Rules on Propane, Cylinders, Propane Tanks and Arcproducing
Frequently Asked Questions
When is a permit required?
A permit is required before any work is commenced on any electrical installation.
What are the permit fees?
Permit fees are based on the total cost of the installation including materials, labour and all reasonable travelling and living expenses incurred by the applicant while absent from his or her place of residence and in the course of carrying out the electrical work.
A minimum fee of $45.00 will cover projects valued up to $500. Permit fees for projects over $500 have been calculated for you.
Who may apply for a permit?
Any individual that is registered as a Qualified Electrical Worker in the Northwest Territories may apply for an Electrical Permit.
May I obtain a permit by mail, facsimile or email?
A permit may be obtained by a qualified electrical worker from any regional electrical inspector by mail, email or in person. Payment is accepted by cash or cheque. A qualified electrical worker can also obtain a permit by facsimile (867-873-0117) from the headquarters office in Yellowknife, with payment made by visa.
A homeowners permit can only be obtained in person from any Regional Inspector.
Qualified electrical workers may also fill out and the online permit applications directly from this web site, sign and submit.
Should I purchase the permit or let the contractor purchase it?
The electrical contractor is required to obtain the permit as part of the project agreement. This is simply because the permit holder is the party responsible for the work and complying with the codes and regulations.
How long is a permit good for?
An installation permit, other than for a temporary consumer's service for construction is valid for one year.
An installation permit for temporary consumer’s service for construction is valid for 90 days.
In both instances an inspector, upon application may grant one or more extensions of an installation permit at no additional fee.
May a permit be voided?
An inspector may cancel an installation permit, other than a temporary consumer's service for construction, where no work has been done under the permit for 90 days or longer, or the holder of the permit fails to comply with any provision contained in the permit, the Electrical Protection Act or the regulations.
The Electrical Inspector may cancel the homeowners permit at his discretion.
May a permit be returned for a refund?
An inspector shall, on the application of the holder of an installation permit or a residential property owners permit, refund all but ($25.00) twenty five dollars of the fee paid if the permit is cancelled; the electrical work authorized by the permit is included in another permit; or the job is cancelled or destroyed before completion.
No person is eligible for a refund of fees under a permit unless an application for refund is made within 90 days of the permit issued and no work has commenced.